Site Name : Local Basic
Total Capacity : 1342.545kWp
Report Date : 20/11-3/12/2023 (Monday-Sunday)
Phase : 1
Capacity: 871.905kWp
Area: Lobby, Auto CNC A, Auto CNC B, Auto CNC C
Mounting Structure
Lobby - 100% Completed
Auto CNC A - 100% Completed
Auto CNC B - 100% Completed
Auto CNC C - 60% Completed
PV Module Lifted on Roof
Total Panel = 1571 pcs
Lobby - 100% Completed
Auto CNC A - 100% Completed
Auto CNC B - 100% Completed
Auto CNC C - 50% Completed
PV Module Installation
Lobby - 100% Completed
Auto CNC A - 100% Completed
Auto CNC B - 100% Completed
Auto CNC C - 50% Completed
DC Trunking - 87% Completed
Inverter Installation - 100% Completed
PVMSB Installation - 0% Completed
AC Trunking - 50% Completed
AC Cable Installation - 0% Completed
Interconnection Works - 0% Completed
———————————————
Phase : 2
Capacity: 470.640kWp
Area: Manual CNC, Casting, Production, Curve Roof
Mounting Structure
Man. CNC - 100% Completed
Casting - 70% Completed
Production - 0% Completed
Curve Roof - 0% Completed
PV Module Lifted on Roof
Total Panel = 848 pcs
Man. CNC - 100% Completed
Casting - 20% Completed
Production - 0% Completed
Curve Roof - 0% Completed
PV Module Installation
Man. CNC - 100% Completed
Casting - 20% Completed
Production - 0% Completed
Curve Roof - 0% Completed
DC Trunking - 50% Completed
Inverter Installation - 100% Completed
PVMSB Installation - 0% Completed
AC Trunking - 0% Completed
AC Cable Installation - 0% Completed
Interconnection Works - 0% Completed